1. COLORED Lacobel (COLORIMO/ EXCELLENT) RAW
The given price includes measurements, production, transport and installation of glass in Szczecin.
Outside the city, an additional fee of PLN 2 net/km applies.
The price does not include silicone treatment, which we can perform as an additionally paid service.
The price is given as a net amount, including VAT.
Delivery time approx. 2-3 weeks from the moment of payment of an advance payment of 50% of the amount and acceptance of the final order.
Introducing any changes will extend the execution of the order.
Please prepare the installation site appropriately (as agreed during measurements):
- dismantling electrical sockets,
- dismantling the faucet,
- dismantling the hood,
- dismantling the kitchen hob,
- dismantling LED lighting,
- and other elements that prevent the installation of glass.
Information regarding the preparation of the installation site will be provided during measurement. In the event of inadequate preparation of the installation site, the Contractor reserves the right to refuse to perform the service and at the same time charge the Ordering Party the amount of PLN 100.00 for unauthorized arrival.
If the electrical sockets are not dismantled, the Contractor may perform the installation by adding an additional fee in accordance with the Additional Services Price List.
2. Lacobel tempered glass
The given price includes measurements, production, transport and installation of glass in Szczecin.
Outside the city, an additional fee of PLN 2 net/km applies.
The price does not include silicone treatment, which we can perform as an additionally paid service.
The price is given as a net amount, including VAT.
Delivery time approx. 4-6 weeks from the moment of payment of an advance payment of 50% of the amount and acceptance of the final order.
Introducing any changes will extend the execution of the order.
Please prepare the installation site appropriately (as agreed during measurements):
- dismantling electrical sockets,
- dismantling the faucet,
- dismantling the hood,
- dismantling the kitchen hob,
- dismantling LED lighting,
- and other elements that prevent the installation of glass.
Information regarding the preparation of the installation site will be provided during measurement. In the event of inadequate preparation of the installation site, the Contractor reserves the right to refuse to perform the service and at the same time charge the Ordering Party the amount of PLN 100.00 for unauthorized arrival.
If the electrical sockets are not dismantled, the Contractor may perform the installation by adding an additional fee in accordance with the Additional Services Price List.
3. Graphics on raw glass
The given price includes measurements, production, transport and installation of glass in Szczecin.
Outside the city, an additional fee of PLN 2 net/km applies.
The price does not include silicone treatment, which we can perform as an additionally paid service.
The price is given as a net amount, including VAT.
Delivery time approx. 4-6 weeks from the moment of payment of an advance payment of 50% of the amount and acceptance of the final order.
Introducing any changes will extend the execution of the order.
Please prepare the installation site appropriately (as agreed during measurements):
- dismantling electrical sockets,
- dismantling the faucet,
- dismantling the hood,
- dismantling the kitchen hob,
- dismantling LED lighting,
- and other elements that prevent the installation of glass.
Information regarding the preparation of the installation site will be provided during measurement. In the event of inadequate preparation of the installation site, the Contractor reserves the right to refuse to perform the service and at the same time charge the Ordering Party the amount of PLN 100.00 for unauthorized arrival.
If the electrical sockets are not dismantled, the Contractor may perform the installation by adding an additional fee in accordance with the Additional Services Price List.
4. Graphics on tempered glass
The given price includes measurements, production, transport and installation of glass in Szczecin.
Outside the city, an additional fee of PLN 2 net/km applies.
The price does not include silicone treatment, which we can perform as an additionally paid service.
The price is given as a net amount, including VAT.
Delivery time approx. 4-8 weeks from the moment of payment of an advance payment of 50% of the amount and acceptance of the final order.
Introducing any changes will extend the execution of the order.
Please prepare the installation site appropriately (as agreed during measurements):
- dismantling electrical sockets,
- dismantling the faucet,
- dismantling the hood,
- dismantling the kitchen hob,
- dismantling LED lighting,
- and other elements that prevent the installation of glass.
Information regarding the preparation of the installation site will be provided during measurement. In the event of inadequate preparation of the installation site, the Contractor reserves the right to refuse to perform the service and at the same time charge the Ordering Party the amount of PLN 100.00 for unauthorized arrival.
If the electrical sockets are not dismantled, the Contractor may perform the installation by adding an additional fee in accordance with the Additional Services Price List.
Notes on Lacobel glass/graphics on glass:
- Before installation, it is essential to dismantle colliding elements that may significantly interfere with the assembly process,
- As a standard, we will leave assembly gaps around the lacobel of approx. 2 mm on each side, however, in the event of significant unevenness in the place where the lacobel is mounted (curvature of walls, cabinets), gaps larger than 2 mm may occur,
- in the case of varnished glass, we do not recommend backlighting (possible uneven paint shine),
- we do not ensure color continuity of the shade in subsequent orders,
- if it is necessary to make another form or forms (forming a whole with more forms), we do not ensure the continuity of the color shade,
- we recommend installation with neutral silicone (especially colors with glitter and silver tint),
- mixing different glass thicknesses will cause color differences in shade,
- if the forms are additionally glued with foil, we do not recommend installation by gluing,
- minor color discoloration is possible, which is caused by occasional defects in the lacquered coating occurring at the level of its production (especially visible in dark colors),
- in case of contact with a heat source (e.g. stove), we do not recommend using lacobel and colorimo glass. We recommend tempered glass painted to order,
- colors presented on the website may not be 100% accurate on your screen. This is related to, among others, with the calibration and settings of your monitor and the quality of the graphics card transducers. This website is not intended to be an absolutely faithful representation of each color, but only to approximate it as best as possible,
- Color tones presented on samplers in the office may not be 100% faithfully reproduced. This is related to, among others, with further new deliveries of paint and glass,
- Colorimo, Lacobel and custom-painted glass should not be combined (possible color incompatibility).
5. Mirror
The given price includes measurements, production, transport and installation of glass in Szczecin.
Outside the city, an additional fee of PLN 2 net/km applies.
The price does not include silicone treatment, which we can perform as an additionally paid service.
The price is given as a net amount, including VAT.
Delivery time approx. 2-3 weeks from the moment of payment of an advance payment of 50% of the amount and acceptance of the final order.
Introducing any changes will extend the execution of the order.
Please prepare the installation site appropriately (as agreed during measurements):
- dismantling electrical sockets,
- dismantling the faucet,
- dismantling the hood,
- dismantling the kitchen hob,
- dismantling LED lighting,
- and other elements that prevent the installation of glass.
Information regarding the preparation of the installation site will be provided during measurement. In the event of inadequate preparation of the installation site, the Contractor reserves the right to refuse to perform the service and at the same time charge the Ordering Party the amount of PLN 100.00 for unauthorized arrival.
If the electrical sockets are not dismantled, the Contractor may perform the installation by adding an additional fee in accordance with the Additional Services Price List.
Comments:
- we do not recommend backlighting,
- we do not ensure color continuity of the shade in subsequent orders,
- if it is necessary to make another form or forms (forming a whole with a larger number of forms purchased from us earlier), we do not ensure the continuity of the color shade,
- Mixing different glass thicknesses will result in color differences in shade.
Notes on shower cabins:
- hardening according to the Polish Standard PN-EN 12150-2,
- we do not recommend backlighting,
- tempered glass contains a SAFETY GLASS mark on the edge of the glass (written information from the customer about waiving marking is required),
- 4mm and 5mm tempered glass has a special sticker (it is not possible to stick it on other glass),
- we perform marking on the glass surface at the customer's request (in any place indicated by the customer),
- the tempering mark is the basis for filing complaints about glass tempering (after removing the sticker from 4-5 mm glass, the tempered glass will also not be subject to complaints),
- We temper the entrusted glass at the customer's responsibility (we do not accept any responsibility for any loss of tempering or damage),
- Tempered glass may have small black threads - precipitated pieces of tin.
Tempering of perforated glass is carried out according to the following principles:
- it is recommended that perforated glass have a hole diameter not smaller than the glass thickness,
- it is recommended that the distance from the edge of the opening to the edge of the glass should not be less than 2 times the thickness of the glass,
- it is recommended that the distance between the edges of 2 holes should not be less than 2 times the thickness of the glass,
- it is recommended that the distance from the edge of the opening to the corner of the glass should not be less than 6 times the thickness of the glass,
- in the case of perforated glass, the frames created after internal cutting out or cutting out the edge should not be smaller than 1/3 of the cutout length.
The nature of the tempering process makes it impossible to obtain a product as flat as annealed glass. The differences depend on the nominal thickness, dimensions and ratios between dimensions.
- signs of small impressions may appear on the glass surface ("roller reflection"),
- during hardening, the glass surface deflects,
- during tempering, small inclusions/bubbles are formed on the glass surface,
- After hardening, spontaneous explosions of glass pieces sometimes occur (this is not subject to complaint),
- small forms made of 4 mm glass are tempered at the customer's risk,
- ornamental glass and 10-12mm colored glass, i.e. antisols (brown, graphite and black), are tempered at the customer's responsibility, the cost of bleeds in tempering is covered by the customer,
- 10 and 12 mm glass has a longer production period (tempered once a week),
- 15 and 19 mm glass has a longer lead time (6-8 weeks),
- for tempering, the glass must have finished edges:
Glass from 4mm to 6mm - blunt edges (lack of grinding may cause chips on the edge up to 3mm)
Glass 8 mm and thicker - polished edges